WEST DANVILLE, CABOT, MARSHFIELD – The Vermont Agency of Transportation (VTrans) planned to continue work on U.S. Rte. 2 from the intersection with Vt. Rte. 15 in West Danville, west through Cabot to the Marshfield town line, Monday, June 9 through Friday, June 13.

Between the hours of 7 a.m. and 6 p.m., motorists should anticipate minor delays and alternating one-way traffic on Rte. 2. Flaggers and Uniformed Traffic Officers will be present to assist motorists through the work zone.
Crews will begin paving the side road approaches and driveway aprons beginning at the intersection of Rte. 2 and Rte. 15 in West Danville and continue west through Cabot toward the Marshfield town line.
On Wednesday, June 11, crews will be grinding the centerline rumble strips in Cabot.
On Wednesday, June 11, and Thursday, June 12, crews will be installing asphaltic plug joints at the bridge near the outlet of Joe’s Pond in West Danville near the intersection of Rte. 15 with Rte. 2.
On Friday, June 13, crews will be installing permanent line markings at the park and ride in West Danville.
A VTrans update on the project status said crews predominantly conducted reclaiming work, milling and filling activities, excavation, and paving in 2024.
The remaining work consists of paving activities, installing markings, placing signage and site restoration and vegetation. The paving activities specifically include paving side road approaches and driveway aprons, grinding the center-line rumble strips, placing pavement markings and placing aggregate shoulders to back up the new pavement.
The project is on schedule to be completed at the end of June 2025, said VTrans.